Lake George Basin Sewer Project (Federal Funds 95%) |
|||
|
|
PROJECT |
COST |
|
|
(1) |
Lake George Village
Wastewater Treatment Plant Upgrade Construction Completed
|
$1,040,274.00 |
|
|
(2) |
Bolton Town Wastewater
Treatment Plant Upgrade Construction 95% Complete |
$1,627,794.00 |
|
|
(3) |
Hague Town Wastewater
Collection System and Treatment Plant Construction Scheduled to begin May 2002 |
$7,920,093.00 |
|
|
(4) |
North Queensbury Town
Wastewater Project Planning for solution of wastewater collection and treatment along east shore of Lake George (Assembly Point, Cleverdale, Rockhurst, Route 9L and Southern portion of Pilot Knob Road)
|
||